New Norwegian offshore standard contracts – NTK 15 & NTK 15 MOD
The Norwegian Total Contract (NTK) has now been updated in a new 2015 version, which is in line with revisions of NTK 15 Mod effectuated in June 2015. The development opens up for individual negotiations of several key terms in the standard contracts as the level of standardization has been reduced, and deadlines included in the contracts have now largely been altered to 21 days in substitution for previous “without undue delay” deadlines.
The Norwegian Total Contract (NTK) has now been updated in a new 2015 version, which is in line with revisions of NTK 15 Mod effectuated in June 2015. The development opens up for individual negotiations of several key terms in the standard contracts as the level of standardization has been reduced, and deadlines included in the contracts have now largely been altered to 21 days in substitution for previous “without undue delay” deadlines.
The Norwegian Total Contract has now been revised, and a 2015 version was issued 20 October 2015. A third version of NTK 15 Mod was issued at the same time, which is meant for traditional modification contracts without the delivery of a new module. This follows the two other versions of NTK 15 MOD that were issued in June 2015, which are both aimed at contracts where a new module is included in the deliverables.
The new NTK 15 and NTK 15 Mod for traditional modification contracts have received largely identical updates to the two versions of NTK 15 Mod issued in the summer. This most recent contract revision development shows that the updates made in June are representative of a new industry standard for the Norwegian offshore contracts.
The main alterations from preceding standards are that the obligation to utilize the standard contracts has been abandoned as the group of operators has been increased to include many other operators, and the level of standardization of key terms within the contracts has been reduced compared to prior standards. Many terms that were previously fixed in the contract have now been omitted, and will be subject to negotiations between the contracting parties under each individual agreement.
The petroleum activity on the Norwegian continental shelf is characterized by a unique and extensive use of standard contracts. These standard contracts have been developed and negotiated in cooperation between the industry’s main operators Statoil (and previously Hydro and Saga) and the main contractor interests since the 1980s, and those operators have been obligated to utilize these standard contract conditions.
The last remaining contract expected to be issued in the ongoing round of revisions is Norwegian Fabrication Contract (NF 07). Based on the content in the contracts revised to date, it is to be expected that this contract will be altered to include similar updates. It is worthwhile for professionals in the offshore industry to note the present revision work laid down in relation to NTK 15 and NTK 15 Mod, as this will be the new industry standard for total offshore contracts in Norway, and most likely for fabrication contracts as well.
The two revisions of NTK 15 and NTK 15 Mod contain parallel revisions. We will for the sake of simplicity only refer to NTK 15 in the following, but the mentioned updates apply to both contracts.
Main Alterations from Preceding Standard
Variation handling regime
The deadlines concerning the issue of certain notices (including Variation Order Requests) from Contractor are changed from “without undue delay” to the absolute deadline of “21 days” after a triggering event. Compliance with this deadline requires a sound back to back agreement system for the Contractor’s subcontracts in order to avoid potential loss of rights in areas covered by subcontractors.
Contrary to the preceding contract, NTK 15 expressly sets out that the Contractor is obliged to act upon and implement a specific written instruction from the Company as soon as this is received, regardless of the parties’ view on whether it constitutes a variation and its potential effects.
The rule is followed up by the introduction of a deadline of 21 days after receipt of a VOR for the Company to issue a DVO or a VO. If no DVO or VO is issued, a DVO is deemed issued, providing the Contractor with the accompanying rights such as provisional compensation and expert decision. This alteration is intended to compensate for the strict duty to immediately implement written instructions from the Company, and to contribute to the identification and potential solution of conflicts at an early stage.
Reduced standardization of liability for liquidated damages
The concrete level of liquidated damages is omitted from the contract, as well as the total cap for this liability, leaving this point to be decided upon in each individual agreement.
Reduced standardization of liability limitations
Similarly as for liquidated damages, the global limitation of liability and the Contractor’s liability cap for accidents/occurences has been left open in the contract, thus these terms will also be subject to individual negotiations.
Risk for Company’s Frame Agreements
Furthermore, alterations have been made on the topic of Subsupplies ordered on the basis of Frame Agreements that the Company requires the Contractor to use, where certain responsibilities have been transferred from the Company to the Contractor. The revised text also provides further clarity, as the corresponding clause in the preceding contracts was perceived as somewhat ambiguous.
Omission of regulations covering maturity of target and fixed prices
Article 21 in NTK 07 which sets out parametres for the establishment of a target price or a fixed price has been dropped from NTK 15. This entails that these points also will be subject to individual negotiations on a contract by contract basis.
Dispute resolution
Article 37 regarding dispute resolutions is altered, as the previous mandatory system of employing an arbiter in order to uncover and potentially solve disagreements during the project has been replaced by a new and voluntary system of Project Integrated Mediation, which is a system that has been employed and positively perceived in certain Norwegian onshore contracts.
Final Remarks
In a similar manner as the firm frequently does for other offshore standard contracts, Haavind is available to hold internal seminars for companies interested in increasing its competence on the topics of NTK 15 and NTK 15 Mod.